    100 Days Program Report

    Jal Jeevan Mission & Swachh Bharat Mission Grameen 2.0
    Sr. No. Particulars Program Completed/Incomplete If completed, provide the related information and Government Resolution / photo / etc. records or its link. If not completed, mention the current status and the timeline for completion of the work.
    Jal Jeevan Mission
    1 9000 villages with 100% household with FHTCs Incomplete Out of the target of 9000 villages, 7070 villages (78%) have been completed. The remaining target is expected to be achieved before the deadline.
    2 Additional 5065 PWS schemes for completion Complete Against the target of 5065 schemes, a total of 5246 schemes (103%) have been completed.
    3 100% source strengthening measures in 5304 critical & vulnerable villages (no. of measures) Complete All 848 measures targeted have been fully completed (100%).

    4 Give Revised Administrative Approval (RAA) of 3000 schemes Incomplete Revised Administrative Approval has been granted for 2843 schemes (94%) out of the target of 3000 schemes. The remaining target is expected to be achieved before the deadline.
    5 Achieving 100% geotagging of Source Complete Out of 1606 targeted sources, geotagging has been completed for all 1606 sources (100%).

    6 Achieving 100% geotagging of Scheme Information Board Complete Geotagging of scheme information boards has been completed for all 1238 targeted schemes (100%).
    7 Achieving 100% coverage of PVTG villages under PM-JANMAN yojana Complete Coverage of PVTG villages under PM-JANMAN yojana has been completed.

    8 Achieving 100% drinking water availability in Schools Complete Out of the 847 targeted schools, drinking water availability has been ensured in all 847 schools (100%).
    9 Achieving 100% drinking water availability in Anganwadi Complete Out of the 1280 targeted Anganwadis, drinking water availability has been ensured in all 1280 Anganwadis (100%).
    10 Targeting preparedness for enabling 10 labs as NABL accredited – District level (Bact. testing) Complete A total of 10 laboratories have been prepared for NABL accreditation.

    11 GSDA – Water saving measures on 30000 hectare (Atal Bhujal) Complete Water saving measures have been implemented across 39,444 hectares, achieving 131% of the target.

    Swachh Bharat Mission Grameen 2.0
    12 Complete SWM arrangement in 8110 Villages Complete Out of 8110 villages, SWM arrangement have been completed in 8110 villages (100%).
    13 Complete LWM arrangement in 6997 Villages Incomplete Out of 6997 villages, LWM arrangement have been completed in 6479 villages (93%). The deadline for the target is until end of August 2025.
    14 Declare 7500 villages ODF Plus Model Incomplete Out of 7500 villages, 6531 villages (87%) have been declared as ODF Plus Model. The deadline for the target is until end of August 2025.
    15 Complete GOBARdhan projects in 9 districts Complete Out of 9 GOBARdhan projects, 10 projects (111%) have been completed.
    16 Completion of 115 FWM units Incomplete Out of 115 plastic waste management projects, 74 projects have been completed. The deadline for the target is until end of August 2025.